Forum Post: Production orders interruption when plan in dynamics NAV 2009 R2

$
0
0

Hi , I use Dynamics NAV  2009 R2  + W1 version.

Manufacturing module.

Key points: Manufacturing policy of items & SKU= MTO (Make to order)   / Capacity constrained resource table update with all work centers load=100%

    24 running company. 3 work shifts each 8 hours. 

I run PW(Planning worksheet) & got FPO(Firm planed order) for item A. Next time again i run PW & got FPO for item B.  Work center (W) has assigned for both item A & B.  Then i change the start time of FPO of item B. 

after that i analysis allocated capacity of work center (W) & realized Work center process continuously but orders are shuffled(interruption)  like this.

Order no           start time        end time         run time   work center

FPO-1              8.00am            8.15AM            15m                  W

FPO-2              8.15AM             8.45AM            30M                  W

FPO-1              8.45AM             9.10AM            25M                  W

Here second order  (FPO-2) interruption with FPO-1 , what i want to do first FPO-1 has to finish first & FPO-2 finish later. Assume Both production order due in same date. 

How can we accomplish this situation in Dynamics NAV using standard functionality.?